Offline field capture register · Revision 01 · Sample excerpt · Not a live plant record

Project
Vejle Plant 2 Commissioning (FAT/SAT)
Site / area
Vejle Plant 2 · sample excerpt
Date
11 OCT 2026
Technician
Lead commissioning engineer

Document hash CRC-32 0x4B78E109

Commissioning blocked by external disciplines (3.5h lost) · 3 blockers

TimePhotoTagIssue / voice transcription
14:02:11UTC
Photo placeholder
+TK1-LT01

Analog level transmitter cable coiled behind frame

Issue: Analog level transmitter cable coiled behind frame. Never landed on sensor head. Electricians signed off terminal X14 as complete.

Suspected component: Terminal strip X14

Action required: EXTERNAL_BLOCKER

OPEN
09:14:22UTC
Photo placeholder
+P2-PE04

Station 2 infeed photoeye is NPN sinking

Issue: Station 2 infeed photoeye PE-04 is NPN sinking, drawings specify PNP sourcing. PLC digital input rack 1 slot 2 bit 4 never goes high.

Suspected component: Wrong sensor part number

Action required: EXTERNAL_BLOCKER

OPEN
11:32:05UTC
Photo placeholder
+S3-GS01

Safety gate 03 door interlock misaligned

Issue: Safety gate 03 door interlock mechanically misaligned. Tongue binds on entry. Vibrations trip Channel B on safety relay K04.

Suspected component: Misaligned latch

Action required: HW_REMEDIATION

PUNCH

OEE guarantees suspended until full clearing of mechanical defects. SI warranty does not cover scrap.